Annual Hours of Delay/Mile: 60,153 Annual Congestion Cost: $4,336,760 County: Bexar Previous Rankings: 880
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Stone Oak Parkway to Comal County Line
Project Types: Capacity Expansion, Express Bus ServiceImprovements include expanding US 281 from a 4 lane divided highway to a 6 lane expressway with frontage roads. It will include 4 general purpose lanes and 2 HOV lanes. This project is divided into two phases. Phase 1 is from LP 1604 to North of Stone Oak Parkway and Phase 2 is form North of Stone Oak Parkway to Comal county line.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 025304138
- Cost Estimate: $178,000,000
- Let Date: FY 2018
- Completion Date: 2023
- Project Data last modified: August 4, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Expansion: SL 1604 to Stone Oak Parkway
Project Types: Capacity Expansion, Express Bus Service, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Signal Operations/ManagementWebsite: http://www.411on281.com/US281EIS/
This project will expand US 281 to 6 lanes expressway with frontage road, 4 lane general purpose and 2 HOV lanes from 1604 to Stone Oak Parkway. It will include the northern interchange connections @ Loop 1604. The second phase will be the construction from Stone Oak to Comal County Line of 6 lane expressway with frontage roads. 4 lanes will be general purpose and 2 lanes will be HOV.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 025304146
- Cost Estimate: $187,000,000
- Let Date: FY 2017
- Completion Date: 2021
- Project Data last modified: August 2, 2021
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 NEX South Phase 1
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/081519.html
I-35 NEX South South Phase 1 extends from I-410 south interchange to the I-410 North interchange. The scope of Phase 1 includes 3 new express lanes in each direction (2 GP + 1 HOV/Special Use Lane) and direct connectors at I-410S. The project will be delivered as a design build. 0017-10-168: I-410 South to I-410 North
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0017-10-168
- Cost Estimate: $700,000,000
- Let Date: FY 2023
- Completion Date: 2029
- Project Data last modified: July 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 NEX (Central)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/division/debt/strategic-projects/alternative-delivery/i35-nex.html
The I-35 NEX project will be phased into three segments: North, Central, and South. The I-35 NEX Central includes limits from IH 410 N to FM 3009. This is a clear initiative project with scope to expand the existing expressway to add 6 additional lanes (4 General Purpose and 2 HOV/Special Purpose). Project will also include direct connectors at IH 410 N and LP 1604 as well as work for ramps, frontage, and bridge from Cibolo Creek to FM 3009. I 35 NEX Central will be delivered as a design build project. 0016-06-047: BEXAR/GUADALUPE COUNTY LINE to FM 3009 0016-07-113: IH 410 N to GUADALUPE/BEXAR COUNTY LINE
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0016-06-047
- Cost Estimate: $278,800,000
- Let Date: FY 2021
- Completion Date: 2027
- Project Data last modified: February 8, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 0016-07-113
- Cost Estimate: $1,343,200,000
- Let Date: FY 2021
- Completion Date: 2027
- Project Data last modified: February 8, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 – Expansion SH 16 to IH 35
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/092319.html
Design-Bid-Build to expand existing expressway to add 6 additional lanes 4 GP and 2 HOV Special Purpose Lanes and Direct Connectors at I 10 interchange
Project Details
- CSJ Number(s) or MTP Reference Numbers: 245202083
- Cost Estimate: $148,000,000
- Let Date: FY 2021
- Completion Date: 2024
- Project Data last modified: February 1, 2024
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 245202128
- Cost Estimate: $200,000,000
- Let Date: FY 2021
- Completion Date: 2025
- Project Data last modified: February 1, 2024
Phase 3
- CSJ Number(s) or MTP Reference Numbers: 245202117
- Cost Estimate: $43,700,000
- Let Date: FY 2021
- Completion Date: 2025
- Project Data last modified: February 1, 2024
Phase 4
- CSJ Number(s) or MTP Reference Numbers: 007208144
- Cost Estimate: $418,000,000
- Let Date: FY 2022
- Completion Date: 2027
- Project Data last modified: February 1, 2024
Phase 5
- CSJ Number(s) or MTP Reference Numbers: 245202130
- Cost Estimate: $55,000,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: February 1, 2024
Phase 6
- CSJ Number(s) or MTP Reference Numbers: 245203113
- Cost Estimate: $126,000,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: February 1, 2024
Phase 7
- CSJ Number(s) or MTP Reference Numbers: 245203087
- Cost Estimate: $180,000,000
- Let Date: FY 2024
- Completion Date: 2027
- Project Data last modified: February 1, 2024
Phase 8
- CSJ Number(s) or MTP Reference Numbers: 245203128
- Cost Estimate: $166,000,000
- Let Date: FY 2028
- Completion Date: 2031
- Project Data last modified: February 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 NEX (North)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/081519.html
I-35 NEX North project limits is from FM 3009 to FM 1003. It is a clear lanes initiative with scope to expand the existing expressway to add 2 new at grade lanes in each direction (1 General Purpose and 1 HOV/Special Use Lane), intersection operational improvements, and reconstruction of overpasses at FM 2252 and Wiederstein Road. The segment from FM1103 to FM3009 will be delivered as Design-bid-build. 0016-06-115: FM 3009 to Guadalupe/Comal County Line 0016-05-111: Guadalupe/Comal County Line to FM 1103
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0016-05-111
- Cost Estimate: $390,000,000
- Let Date: FY 2027
- Completion Date: Unknown
- Project Data last modified: July 31, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 0016-06-115
- Cost Estimate: $141,000,000
- Let Date: FY 2027
- Completion Date: Unknown
- Project Data last modified: July 31, 2023
Regionally:
VIA Frequency Program CMAQ
Provide improved bus frequency along US 281 (Route 7) and I 410 (Route 552) ; increased frequency has a direct link to increase ridership which could reduce VMT or at least hold it steady and population increase.
Project Details
- CSJ Number(s): 091512673
- Cost Estimate: $7,037,144
- Let Date: FY 2020
- Completion Date: Unknown
- Project Data last modified: February 5, 2020
Phase 2
- CSJ Number(s): 091512680
- Cost Estimate: $2,181,429
- Let Date: FY 2021
- Completion Date: Unknown
- Project Data last modified: February 5, 2020
Phase 3
- CSJ Number(s): 091512686
- Cost Estimate: $2,181,427
- Let Date: FY 2022
- Completion Date: Unknown
- Project Data last modified: February 5, 2020
Highway Emergency Response Operations (HERO)
Provide emergency response service along I 35, US 281, I 10 , I 37, LP 410. Provide assistance to disabled vehicles and crashes.
Project Details
- CSJ Number(s): 0915-00-212
- Cost Estimate: $2,500,000
- Let Date: FY 2020
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Phase 2
- CSJ Number(s): 0915-00-213
- Cost Estimate: $5,500,000
- Let Date: FY 2020
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Phase 3
- CSJ Number(s): 0915-00-214
- Cost Estimate: $5,500,000
- Let Date: FY 2021
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Phase 4
- CSJ Number(s): 0915-00-227
- Cost Estimate: $5,500,000
- Let Date: FY 2022
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Operational Management
Incident Management System, access management, signalization and traffic flow improvements, railroad crossing improvements, construction coordination, and freight management.
Advanced Transportation Systems
Bus rapid transit, managed lanes, commuter rail service.
ITS – US 281 and SL 1604
Intelligent Transportation Systems: advanced traffic management, advanced public transit system, emergency management. Install CCTV, DMS, Vehicle Detection using fiber. US 281 (Nakoma to SL 1604) ; SL 1604 (I 10 -US 281) and SL 1604 (US 281-I 35)
Project Details
- CSJ Number(s): 025304158
- Cost Estimate: $1,600,000
- Let Date: FY 2019
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Transit
Public Transit Improvements for the region include transit service enhancements, transit facilities, and ridership incentives.
Travel Demand Management
Commute Solutions program aims to reduce automobile use and congestion through AAMPO’s rideshare program, work schedule coordination, telecommuting, walkable community program, and trip planning.
Pedestrian Improvements
The 2012 Bexar County/San Antonio MPO produced the Pedestrian Safety Action Plan which outlines network improvements needed to encourage walking in the current transportation system.
Planned for Transit:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Park-and-Ride
Project Types: Express Bus Service, Local Bus Service, Park-and-RideUS 281 North Park-and-Ride at Stone Oak is one of six major transit improvements scheduled for construction in FY 2015. VIA received environmental clearance for the US 281 Park-and-Ride in the summer of 2013.
Project Details
- CSJ Number(s):
- Let Date: FY 2015
- Completion Date: Unknown
- Project Data last modified: November 5, 2019
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Expansion: SL 1604 to Stone Oak Parkway
Project Types: Capacity Expansion, Express Bus Service, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Signal Operations/ManagementWebsite: http://www.411on281.com/US281EIS/
This project will expand US 281 to 6 lanes expressway with frontage road, 4 lane general purpose and 2 HOV lanes from 1604 to Stone Oak Parkway. It will include the northern interchange connections @ Loop 1604. The second phase will be the construction from Stone Oak to Comal County Line of 6 lane expressway with frontage roads. 4 lanes will be general purpose and 2 lanes will be HOV.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 025304146
- Cost Estimate: $187,000,000
- Let Date: FY 2017
- Completion Date: 2021
- Project Data last modified: August 2, 2021