Annual Hours of Delay/Mile: 275,505 Annual Congestion Cost: $56,475,401 County: Bexar Previous Rankings: 27
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 – Expansion SH 16 to IH 35
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/092319.html
Design-Bid-Build to expand existing expressway to add 6 additional lanes 4 GP and 2 HOV Special Purpose Lanes and Direct Connectors at I 10 interchange
Project Details
- CSJ Number(s) or MTP Reference Numbers: 245202083
- Cost Estimate: $148,000,000
- Let Date: FY 2021
- Completion Date: 2024
- Project Data last modified: February 1, 2024
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 245202128
- Cost Estimate: $200,000,000
- Let Date: FY 2021
- Completion Date: 2025
- Project Data last modified: February 1, 2024
Phase 3
- CSJ Number(s) or MTP Reference Numbers: 245202117
- Cost Estimate: $43,700,000
- Let Date: FY 2021
- Completion Date: 2025
- Project Data last modified: February 1, 2024
Phase 4
- CSJ Number(s) or MTP Reference Numbers: 007208144
- Cost Estimate: $418,000,000
- Let Date: FY 2022
- Completion Date: 2027
- Project Data last modified: February 1, 2024
Phase 5
- CSJ Number(s) or MTP Reference Numbers: 245202130
- Cost Estimate: $55,000,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: February 1, 2024
Phase 6
- CSJ Number(s) or MTP Reference Numbers: 245203113
- Cost Estimate: $126,000,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: February 1, 2024
Phase 7
- CSJ Number(s) or MTP Reference Numbers: 245203087
- Cost Estimate: $180,000,000
- Let Date: FY 2024
- Completion Date: 2027
- Project Data last modified: February 1, 2024
Phase 8
- CSJ Number(s) or MTP Reference Numbers: 245203128
- Cost Estimate: $166,000,000
- Let Date: FY 2028
- Completion Date: 2031
- Project Data last modified: February 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 Operational Improvements – Nac, Huebner, Bitters
Project Types: Interchange/Intersection Improvements, Operation ImprovementsOperational Improvements along Loop 1604 are planned as interim improvements to the added capacity expansion; constructing turn-a-rounds. These improvements will be at the intersections of Nacogdoches, Huebner, and Bitters.
Project Details
- CSJ Number(s): 245203120
- Cost Estimate: $2,400,000
- Let Date: FY 2018
- Completion Date: 2019
- Project Data last modified: January 29, 2021
Phase 2
- CSJ Number(s): 245202119
- Cost Estimate: $4,900,000
- Let Date: FY 2018
- Completion Date: 2019
- Project Data last modified: January 29, 2021
Phase 3
- CSJ Number(s): 245203118
- Cost Estimate: $9,100,000
- Let Date: FY 2018
- Completion Date: 2020
- Project Data last modified: January 29, 2021
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 ITS Install
Project Type: Intelligent Transportation SystemsFrom I 10 W to US 281 and then 281 to I 35; Install ITS infrastructure.
Project Details
- CSJ Number(s): 2452-02-123
- Cost Estimate: $191,000
- Let Date: FY 2019
- Completion Date: 2023
- Project Data last modified: February 2, 2024
Phase 2
- CSJ Number(s): 2452-03-124
- Cost Estimate: $930,000
- Let Date: FY 2019
- Completion Date: 2023
- Project Data last modified: February 2, 2024
Phase 3
- CSJ Number(s): 0253-04-158
- Cost Estimate: $1,200,000
- Let Date: FY 2019
- Completion Date: 2023
- Project Data last modified: February 2, 2024
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 46 Improvements (Bentwood Dr to FM 3159)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Operation Improvements, Signal Operations/ManagementWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/sh46-bulverde.html
Expand from 2 lanes to 6 lanes with raised median or center turn lane.
Project Details
- MTP Reference Numbers: 0215-01-051
- Cost Estimate: $51,900,000
- Let Date: FY 2033
- Completion Date: Unknown
- Project Data last modified: August 2, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 46 Improvements (Bulverde Road to Farhills)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Operation Improvements, Signal Operations/ManagementWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/sh46-bulverde.html
Expand from 2 lanes to 6 lanes with raised median or center turn lane.
Project Details
- MTP Reference Numbers: 0215-07-049
- Cost Estimate: $530,000,000
- Let Date: FY 2033
- Completion Date: Unknown
- Project Data last modified: August 2, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 NEX (North)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/081519.html
I-35 NEX North project limits is from FM 3009 to FM 1003. It is a clear lanes initiative with scope to expand the existing expressway to add 2 new at grade lanes in each direction (1 General Purpose and 1 HOV/Special Use Lane), intersection operational improvements, and reconstruction of overpasses at FM 2252 and Wiederstein Road. The segment from FM1103 to FM3009 will be delivered as Design-bid-build. 0016-06-115: FM 3009 to Guadalupe/Comal County Line 0016-05-111: Guadalupe/Comal County Line to FM 1103
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0016-05-111
- Cost Estimate: $390,000,000
- Let Date: FY 2027
- Completion Date: Unknown
- Project Data last modified: July 31, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 0016-06-115
- Cost Estimate: $141,000,000
- Let Date: FY 2027
- Completion Date: Unknown
- Project Data last modified: July 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
FM 1535 South
Website: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/071619.htmlConstruct 2 way left turn lane, bike lanes, and sidewalks from LP 1604 to Huebner road.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0658-01-045
- Cost Estimate: $15,500,000
- Let Date: FY 2021
- Completion Date: 2023
- Project Data last modified: November 6, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
FM 1535 North
Website: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/042618.htmlExpand form 2 to 4 lanes with raised median or center turn lane, bike lanes, and sidewalks.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0658-01-044
- Cost Estimate: $5,700,000
- Let Date: FY 2020
- Completion Date: 2022
- Project Data last modified: November 6, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Stone Oak Parkway to Comal County Line
Project Types: Capacity Expansion, Express Bus ServiceImprovements include expanding US 281 from a 4 lane divided highway to a 6 lane expressway with frontage roads. It will include 4 general purpose lanes and 2 HOV lanes. This project is divided into two phases. Phase 1 is from LP 1604 to North of Stone Oak Parkway and Phase 2 is form North of Stone Oak Parkway to Comal county line.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 025304138
- Cost Estimate: $178,000,000
- Let Date: FY 2018
- Completion Date: 2023
- Project Data last modified: August 4, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Study SL 1604 to I 410
Project Types: Study, Capacity Expansion, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation ImprovementsThe US 281 feasibility study developed and evaluated high-level concepts for the addition of high occupancy vehicle (HOV)/transit lanes, one in each direction.
Project Details
- CSJ Number(s): 0915-12-573
- Let Date: FY 2033
- Completion Date: Unknown
- Project Data last modified: February 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 Feasibility Study SH 151 to SH 16
Project Types: Study, Capacity Expansion, Interchange/Intersection Improvements, Operation ImprovementsFeasibility study for operational improvements along SL 1604 from SH 151 to SH 16.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 2452-01-068
- Study Cost: $22,900,000
- Let Date: FY 2033
- Completion Date: Unknown
- Project Data last modified: February 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 46 Improvements (Farhills to Bentwood)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Operation Improvements, Signal Operations/ManagementWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/sh46-bulverde.html
Expanding from 2 lanes to 6 lanes with raised median or center turn lane. 0215-07-027: Farhills Dr. to US 281 0215-01-044: US 281 to Bentwood
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0215-01-044
- Cost Estimate: $31,900,000
- Let Date: FY 2022
- Completion Date: Unknown
- Project Data last modified: August 2, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 0215-07-027
- Cost Estimate: $27,600,000
- Let Date: FY 2022
- Completion Date: Unknown
- Project Data last modified: August 2, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
Wurzbach Parkway Project
Project Types: Interchange/Intersection Improvements, Operation Improvements, Signal Operations/ManagementWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/wurzbach-parkway-lockhill-selma-nwmilitary-highway.html
FROM LOCKHILL SELMA ROAD TO FM 1535 EXPAND 4 TO 6 LANES DIVIDED AND INTERSECTION OPERATIONAL IMPROVEMENTS INCLUDING NEW TURN LANES AND IMPROVED SIGNAL OPERATION AT FM 1535
Project Details
- CSJ Number(s) or MTP Reference Numbers: 7774-01-001
- Cost Estimate: $8,000,000
- Let Date: FY 2020
- Completion Date: 2022
- Project Data last modified: November 29, 2022
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 NEX (Central)
Project Types: Capacity Expansion, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/division/debt/strategic-projects/alternative-delivery/i35-nex.html
The I-35 NEX project will be phased into three segments: North, Central, and South. The I-35 NEX Central includes limits from IH 410 N to FM 3009. This is a clear initiative project with scope to expand the existing expressway to add 6 additional lanes (4 General Purpose and 2 HOV/Special Purpose). Project will also include direct connectors at IH 410 N and LP 1604 as well as work for ramps, frontage, and bridge from Cibolo Creek to FM 3009. I 35 NEX Central will be delivered as a design build project. 0016-06-047: BEXAR/GUADALUPE COUNTY LINE to FM 3009 0016-07-113: IH 410 N to GUADALUPE/BEXAR COUNTY LINE
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0016-06-047
- Cost Estimate: $278,800,000
- Let Date: FY 2021
- Completion Date: 2027
- Project Data last modified: February 8, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 0016-07-113
- Cost Estimate: $1,343,200,000
- Let Date: FY 2021
- Completion Date: 2027
- Project Data last modified: February 8, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 10 HOV Special Use Study
Project Types: Study, Capacity Expansion, Operation ImprovementsFeasibility study to determine future transportation envelope and operational improvements
Project Details
- CSJ Number(s) or MTP Reference Numbers: 007208142
- Study Cost: $780,000
- Let Date: FY 2018
- Completion Date: 2020
- Project Data last modified: July 31, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 007212199
- Study Cost: $2,860,000
- Let Date: FY 2018
- Completion Date: 2020
- Project Data last modified: July 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SL 1604 Expansion ( FM 78 to I 10E)
Project Type: Capacity ExpansionWebsite: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/102418.html
Loop 1604 (From FM 78 to I-10E) improvements would consist of expanding the existing 4-lane divided roadway to a 4-lane expressway with frontage roads, grade-separated intersections, and operational improvements.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 245203111
- Cost Estimate: $246,000,000
- Let Date: FY 2032
- Completion Date: 2034
- Project Data last modified: February 1, 2024
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 2452-03-133
- Cost Estimate: $228,000,000
- Let Date: FY 2033
- Completion Date: 2035
- Project Data last modified: February 1, 2024
Regionally:
ITS – US 281 and SL 1604
Intelligent Transportation Systems: advanced traffic management, advanced public transit system, emergency management. Install CCTV, DMS, Vehicle Detection using fiber. US 281 (Nakoma to SL 1604) ; SL 1604 (I 10 -US 281) and SL 1604 (US 281-I 35)
Project Details
- CSJ Number(s): 025304158
- Cost Estimate: $1,600,000
- Let Date: FY 2019
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Planned for Transit:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 10 HOV Special Use Study
Project Types: Study, Capacity Expansion, Operation ImprovementsFeasibility study to determine future transportation envelope and operational improvements
Project Details
- CSJ Number(s) or MTP Reference Numbers: 007208142
- Study Cost: $780,000
- Let Date: FY 2018
- Completion Date: 2020
- Project Data last modified: July 31, 2023
Phase 2
- CSJ Number(s) or MTP Reference Numbers: 007212199
- Study Cost: $2,860,000
- Let Date: FY 2018
- Completion Date: 2020
- Project Data last modified: July 31, 2023
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled