Annual Hours of Delay/Mile: 88,022 Annual Congestion Cost: $7,769,686 County: Nueces Previous Rankings: 35
Projects
Corridor Specific:
No improvements are currently planned.
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 286 Freeway Extension
Project Types: Capacity Expansion, Grade SeparationSH 286 serves as a parallel route to South Staples St. The proposed SH 286 project includes capacity improvements/upgrade of existing 2-lane highway to 4-lane freeway from FM 43 (Weber Rd.) to FM 2444 (Staples St.) which will provide commuters with an alternate route to and from the Southside of Corpus Christi.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0326-01-056
- Cost Estimate: $50,000,000
- Let Date: FY 2024
- Completion Date: 2028
- Project Data last modified: February 9, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 358 Ramp Reversal
Project Type: Operation ImprovementsAs part of the SH 358 ramp reversal improvements identified in the MTP, additional access road queuing lengths and signalization improvements at SH 358/South Staples Street would improve traffic flow and reduce delay in the vicinity of the freeway.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 061701170
- Cost Estimate: $42,700,000
- Let Date: FY 2017
- Completion Date: 2023
- Project Data last modified: February 9, 2023
Regionally:
Operational Management
Regional strategies include access management and signalization and traffic flow improvements.
ITS
Transit
Regional transit strategies include service enhancements, upgraded transit facilities, and ridership incentives all to increase ridership in the area.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled