Annual Hours of Delay/Mile: 283,473 Annual Congestion Cost: $43,557,420 County: Harris Previous Rankings: 58
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610 S from SH 35 (SS 5/Mykawa) to SH 288
Project Types: Capacity Expansion, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation Improvements. Reconstruct IH-610 South Loop Freeway from SH 288 to SH 35 (SS 5/Mykawa) • Upgrade the reconstructed roadway to meet current design criteria. • Address frontage road connectivity. • Provide appropriate connections to the proposed SH 35 project
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-16-159, 0271-16-138, 0271-16-139
- Cost Estimate: $175,500,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610 S from IH 45 to SH 35 (SS 5/Mykawa)
Project Types: Capacity Expansion, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation ImprovementsIH 610 S from IH 45 to SH 35 (SS 5/Mykawa) - reconstruct freeway including TSM improvements.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-16-158
- Cost Estimate: $102,400,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610 at SH 288 Reconstruct Main Lanes and Construct Overpass
Project Types: Capacity Expansion, Grade Separation, Operation ImprovementsIH 610 at SH 288 (W of Cambridge to W of Scott St) reconstruct main lanes, frontage road and construct overpass at Cambridge St/Almeda Rd/UPRR.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-16-140
- Cost Estimate: $116,900,000
- Let Date: FY 2019
- Completion Date: 2025
- Project Data last modified: October 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 45/IH 610 Direct Connectors
Project Types: Interchange/Intersection Improvements, Operation ImprovementsConstruct direct connectors on IH 45 at IH 610.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-606,607
- Cost Estimate: $670,000,000
- Let Date: FY 2016
- Completion Date: 2023
- Project Data last modified: October 31, 2023
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment A) from Griggs Rd to IH 45/Spur 5
Project Types: Capacity Expansion, Operation ImprovementsConstruct 8-lane freeway on new location (Segment A)
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0178-09-018
- Cost Estimate: $93,900,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment C) Mainlanes from Dixie to N of Griggs Rd and IH 610/SH 35 Interchange North
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection ImprovementsConstruct IH 610/SH 35 interchange (North DCs) and construct SH 35 8-lane freeway on new location from Dixie to N of Griggs Rd
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-16-111, 0178-09-020
- Cost Estimate: $311,500,000
- Let Date: FY 2026
- Completion Date: 2030
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610/SH 35 Interchange South
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection ImprovementsConstruct IH 610/SH 35 interchange (South DCs)
Project Details
- MTP Reference Numbers: 0271-16-152
- Cost Estimate: $168,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment B) from Dixie Drive to Long Drive (Frontage Roads)
Project Types: Capacity Expansion, Grade SeparationConstruct 2-lane frontage roads on new location (Segment B)
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0178-09-019
- Cost Estimate: $32,200,000
- Let Date: FY 2026
- Completion Date: 2029
- Project Data last modified: October 30, 2023
Regionally:
No improvements are currently planned.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled