Annual Hours of Delay/Mile: 210,949 Annual Congestion Cost: $38,914,032 County: Harris Previous Rankings: 78
Projects
Corridor Specific:
IH 610E: Widening from IH 10 (E) to IH 45 (S)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsReconstruct and widen from 8 to 12 lanes and add 4 new managed lanes.
Project Details
- MTP Reference Numbers: 0271-15-102, 0502-01-246
- Cost Estimate: $224,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: November 1, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 225 PEL: IH 610 East to SH 146/Barbours Cut
Project Types: Study, Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsSH 225 PEL Study: IH 610 East to SH 146/Barbours Cut
Project Details
- MTP Reference Numbers: 0502-01-228
- Study Cost: $6,400,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610 at Houston Ship Channel
Project Types: Grade Separation, Interchange/Intersection ImprovementsReconstruct the Houston Ship Channel Bridge and increase vertical clearances.
Project Details
- MTP Reference Numbers: 0271-15-096
- Cost Estimate: $1,792,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
SH 225 Widening and Reconstruction of Interchange at IH 610
Project Types: Capacity Expansion, Interchange/Intersection ImprovementsSH 225 Widening from 6 to 8 main lanes from IH 610 to Red Bluff and Reconstruction of Interchange at IH 610/SH 225.
Project Details
- MTP Reference Numbers: 0502-01-226
- Cost Estimate: $280,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: November 1, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 45/IH 610 Direct Connectors
Project Types: Interchange/Intersection Improvements, Operation ImprovementsConstruct direct connectors on IH 45 at IH 610.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-606,607
- Cost Estimate: $670,000,000
- Let Date: FY 2016
- Completion Date: 2023
- Project Data last modified: October 31, 2023
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 610/SH 35 Interchange South
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection ImprovementsConstruct IH 610/SH 35 interchange (South DCs)
Project Details
- MTP Reference Numbers: 0271-16-152
- Cost Estimate: $168,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment C) Mainlanes from Dixie to N of Griggs Rd and IH 610/SH 35 Interchange North
Project Types: Capacity Expansion, Grade Separation, Interchange/Intersection ImprovementsConstruct IH 610/SH 35 interchange (North DCs) and construct SH 35 8-lane freeway on new location from Dixie to N of Griggs Rd
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-16-111, 0178-09-020
- Cost Estimate: $311,500,000
- Let Date: FY 2026
- Completion Date: 2030
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment A) from Griggs Rd to IH 45/Spur 5
Project Types: Capacity Expansion, Operation ImprovementsConstruct 8-lane freeway on new location (Segment A)
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0178-09-018
- Cost Estimate: $93,900,000
- Let Date: FY 2023
- Completion Date: 2026
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 35 (Segment B) from Dixie Drive to Long Drive (Frontage Roads)
Project Types: Capacity Expansion, Grade SeparationConstruct 2-lane frontage roads on new location (Segment B)
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0178-09-019
- Cost Estimate: $32,200,000
- Let Date: FY 2026
- Completion Date: 2029
- Project Data last modified: October 30, 2023
Regionally:
No improvements are currently planned.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled