Annual Hours of Delay/Mile: 306,543 Annual Congestion Cost: $35,077,594 County: Bexar Previous Rankings: 49
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Interchange Study (Basse Road and Jones Maltsberger)
Project Types: Study, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/get-involved/about/hearings-meetings/san-antonio/101818.html
Innovative diverging diamond interchange intersections at Jones Maltsberger and ramp revisions at Basse
Project Details
- CSJ Number(s): 0073-08-198
- Study Cost: $8,300,000
- Let Date: FY 2032
- Completion Date: Unknown
- Project Data last modified: August 4, 2023
Phase 2
- CSJ Number(s): 0073-08-199
- Study Cost: $4,000,000
- Let Date: FY 2032
- Completion Date: Unknown
- Project Data last modified: August 4, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 410 Operational Improvements (Ingram to NW Military)
Project Types: Study, Interchange/Intersection Improvements, Operation ImprovementsStudy to Identify and rank bottlenecks in Bexar County
Project Details
- CSJ Number(s):
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: April 26, 2021
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 410 Interchange Improvements at US 281/San Pedro
Project Types: Study, Interchange/Intersection Improvements, Operation ImprovementsWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/i410-us281-study.html
Operational improvements at the interchange of IH 410 at US 281 and San Pedro including direct connector improvement from US 281 to IH 410 wb; ramp revisions, frontage road and intersection improvements.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 052104285
- Estimated Project Cost: $151,000,000
- Let Date: FY 2026
- Completion Date: Unknown
- Project Data last modified: August 1, 2023
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
Wurzbach Parkway Project
Project Types: Interchange/Intersection Improvements, Operation Improvements, Signal Operations/ManagementWebsite: https://www.txdot.gov/inside-txdot/projects/studies/san-antonio/wurzbach-parkway-lockhill-selma-nwmilitary-highway.html
FROM LOCKHILL SELMA ROAD TO FM 1535 EXPAND 4 TO 6 LANES DIVIDED AND INTERSECTION OPERATIONAL IMPROVEMENTS INCLUDING NEW TURN LANES AND IMPROVED SIGNAL OPERATION AT FM 1535
Project Details
- CSJ Number(s) or MTP Reference Numbers: 7774-01-001
- Cost Estimate: $8,000,000
- Let Date: FY 2020
- Completion Date: 2022
- Project Data last modified: November 29, 2022
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
Wurzbach Parkway Construction
Project Type: Capacity ExpansionThe Wurzbach Parkway (under construction) will serve as an alternate east-west route for SL 1604 and IH 410, improving congestion on those corridors by allowing traffic to divert from these congested corridors onto the Parkway. This project is projected to be open summer of 2015.
Project Details
- CSJ Number(s):
- Let Date: Unknown
- Completion Date: 2015
- Project Data last modified: October 19, 2018
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
I 35 Downtown Study
Project Types: Study, Capacity Expansion, Operation ImprovementsThe study will identify needed added capacity, operational or other improvements on the IH 10, IH 35, IH 37, US 90 and US 281 corridors in downtown San Antonio to address congestion. Earlier PEL studies recommended making improvements to potential alternative/parallel routes to this segment of I-35 due to the complexity and potentially controversial nature of rebuilding and expanding the current facility. The IH 35 downtown study would build upon the earlier PEL studies and carry feasibility study recommendations forward through schematic and environmental clearance.
Project Details
- MTP Reference Numbers: 091512688
- Study Cost: $16,800,000
- Let Date: FY 2020
- Completion Date: Unknown
- Project Data last modified: February 8, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
US 281 Study SL 1604 to I 410
Project Types: Study, Capacity Expansion, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation ImprovementsThe US 281 feasibility study developed and evaluated high-level concepts for the addition of high occupancy vehicle (HOV)/transit lanes, one in each direction.
Project Details
- CSJ Number(s): 0915-12-573
- Let Date: FY 2033
- Completion Date: Unknown
- Project Data last modified: February 1, 2024
Regionally:
Operational Management
Incident Management System, access management, signalization and traffic flow improvements, railroad crossing improvements, construction coordination, and freight management.
Advanced Transportation Systems
Bus rapid transit, managed lanes, commuter rail service.
ITS – US 281 and SL 1604
Intelligent Transportation Systems: advanced traffic management, advanced public transit system, emergency management. Install CCTV, DMS, Vehicle Detection using fiber. US 281 (Nakoma to SL 1604) ; SL 1604 (I 10 -US 281) and SL 1604 (US 281-I 35)
Project Details
- CSJ Number(s): 025304158
- Cost Estimate: $1,600,000
- Let Date: FY 2019
- Completion Date: Unknown
- Project Data last modified: February 4, 2020
Transit
Public Transit Improvements for the region include transit service enhancements, transit facilities, and ridership incentives.
Travel Demand Management
Commute Solutions program aims to reduce automobile use and congestion through AAMPO’s rideshare program, work schedule coordination, telecommuting, walkable community program, and trip planning.
Pedestrian Improvements
The 2012 Bexar County/San Antonio MPO produced the Pedestrian Safety Action Plan which outlines network improvements needed to encourage walking in the current transportation system.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled