Annual Hours of Delay/Mile: 146,463 Annual Congestion Cost: $21,244,760 County: Tarrant Previous Rankings: 77
Projects
Corridor Specific:
No improvements are currently planned.
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Tarrant Express (NTE) Segment 3A
Project Types: Capacity Expansion, Managed Lanes/TollWebsite: http://www.northtarrantexpress.com/
The interim Segment 3A of the North Tarrant Express (NTE) will provide two new managed lanes in each direction along IH 35W from IH 30 to IH 820. The ultimate design will expand the two general purpose lanes to four lanes in each direction. The interim solution provides for discontinuous frontage roads as they exist, the ultimate will provide continuous frontage roads.
Project Details
- CSJ Number(s): 0014-16-179
- Cost Estimate: $130,000,000
- Let Date: FY 2014
- Completion Date: 2018
- Project Data last modified: May 1, 2024
Phase 2
- CSJ Number(s): 0014-16-252
- Cost Estimate: $535,714,000
- Let Date: FY 2036
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Phase 3
- CSJ Number(s): 0014-16-268
- Cost Estimate: $1,600,000,000
- Let Date: FY 2037
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Regionally:
No improvements are currently planned.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled