Annual Hours of Delay/Mile: 140,318 Annual Congestion Cost: $29,369,986 County: Tarrant Previous Rankings: 127
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 35W; S OF ALTAMESA TO SH 174
Reconstruct & widen 6 to 11 lanes from Altamesa Blvd to Everman Pkwy, & reconstruct & widen 6 to 10 lanes from Everman Pkwy To SH 174 with continuous 4/6 to continuous 4/8 lane one way FR & construct 2 lane NB CD, S of FM 1187, & shared use path.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0014-02-050
- Cost Estimate: $738,304,000
- Let Date: FY 2036
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 35W; Garden Acres to Alsbury
CONSTRUCTION OF NEW INTERCHANGE IH 35W AT FM 1187, WITH 4/6 LANE CONTINUOUS TO 4/8 LANE CONTINUOUS ONE WAY FR, RAMP MODIFICATIONS INCLUDING NEW RAMPS, CONSTRUCT 0 TO 2 NORTHBOUND CD LANES, AND SHARED USE PATH
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0014-02-055
- Cost Estimate: $151,786,000
- Let Date: FY 2033
- Completion Date: 2036
- Project Data last modified: May 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 35W: IH 20 to South of Altamesa
Reconstruct and widen 6 to 11 lanes with continuous 4/6 to 4/6 lane frontage roads and shared use path.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0014-16-285
- Cost Estimate: $90,229,000
- Let Date: FY 2036
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 35W; FM 3391/ E. Renfro TO S OF US 67
Reconstruct and widen 4 to 6 lanes with 2/4 discontinuous one way frontage road lanes to 4/6 continuous one way frontage road lanes and add shared use path.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0014-03-098
- Cost Estimate: $574,406,000
- Let Date: FY 2036
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH-35W: SH 174 to FM 3391/E Renfro Street
Reconstruct and widen 4 to 6 mainlanes with continuous 4/6 to 4/6 continuous lane one way frontage roads & shared use path.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0014-03-106
- Cost Estimate: $105,349,000
- Let Date: FY 2036
- Completion Date: 2039
- Project Data last modified: May 1, 2024
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
SH 174: IH 35W to Renfro St
Reconstruct 6 to 4 lanes and 2 lane two-way to 2 lane one-way continuous frontage roads and construct shared use path
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0019-01-149
- Cost Estimate: $103,219,000
- Let Date: FY 2036
- Completion Date: Unknown
- Project Data last modified: November 17, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
FM 3391; IH 35W TO E OF CR 602
Project Type: Capacity ExpansionWIDEN FROM 2 LANES TO 6 LANES FROM IH 35W TO HURST AVENUE AND 2 LANES TO 4 LANES FROM HURST AVENUE TO CR 602
Project Details
- CSJ Number(s) or MTP Reference Numbers: 3372-01-010
- Cost Estimate: $44,643,000
- Let Date: FY 2029
- Completion Date: 2032
- Project Data last modified: May 1, 2024
Regionally:
No improvements are currently planned.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled