Annual Hours of Delay/Mile: 250,581 Annual Congestion Cost: $33,455,345 County: Harris Previous Rankings: 72
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 East PEL: IH 69 to SH 99
Project Types: Study, Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Managed Lanes/Toll, Operation ImprovementsIH 10 East PEL Study: IH 69 to SH 99
Project Details
- MTP Reference Numbers: 0912-00-535
- Study Cost: $5,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Houston Highway Improvement Project Segment 3C-1 and 3C-2
Project Types: Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation Improvements, Other System ModificationNHHIP Segment 3C-1 and 3C-2: IH-10 at IH-69 Interchange: Reconstruct interchange to add IH-10 non-toll managed lanes and realign IH-45. IH-10: IH-69 to IH-45 North Freeway: Reconstruct to add IH-10 non-toll managed lanes for traffic bypassing Downtown. Access to local streets from IH-10 would be maintained via reconstructed general purpose lanes. Reconstruct the IH-10 interchange with IH-45. IH-10 at IH-45 Interchange: Reconstruction interchange to add IH-10 non-toll managed lanes and realign IH-45.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-599, 0500-08-001
- Cost Estimate: $2,724,000,000
- Let Date: FY 2027
- Completion Date: 2033
- Project Data last modified: October 30, 2023
IH 10 Expansion: IH 610 to Spur 330
Project Type: Capacity ExpansionReconstruct and widen from 8 to 10 main lanes on IH 10 from IH 610 to Spur 330.
Project Details
- MTP Reference Numbers: 0508-01-375,376
- Cost Estimate: $539,840,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 31, 2023
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Houston Highway Improvement Project Segment 3D
Project Types: Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation Improvements, Other System ModificationNHHIP Segment 3D: IH-69: IH-45 Gulf Freeway to Buffalo Bayou: Depress and widen IH-69 from IH-45 Gulf Freeway to south of Buffalo Bayou. Reconstruct IH-69 interchanges with IH-45 Gulf Freeway. IH-45 Pierce Elevated: Re-align IH-45 from its current location on the west side of Downtown to be parallel with IH-69. Construct connectors on the west side of downtown providing access between the highway and local streets.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-598, 0500-03-601
- Cost Estimate: $1,578,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Houston Highway Improvement Project Segment 2A
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsNHHIP Segment 2A IH-45: IH-610 to IH-10: Reconstruct IH-45 general purpose lanes from north of IH-610 to north of IH-10. Reconstruct and expand existing reversible single lane high-occupancy vehicle facility to be four lanes (two in each direction) for high-occupancy and transit vehicles.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-560
- Cost Estimate: $489,100,000
- Let Date: FY 2031
- Completion Date: 2035
- Project Data last modified: October 30, 2023
Regionally:
Traffic Management Center (Houston)
Houston TranStar, a consortium of local governments in partnership with the state, is responsible for transportation operations and emergency management in the greater Houston area.
Pedestrian Improvements (Houston)
Strategically enhance bicycle and pedestrian infrastructure throughout the H-GAC region.
METRO Vanpool (Houston)
METRO supports the regional vanpool program which includes approximately 700 vans, 7,100 participants, 200,000 trips per month, 6,000,000 passenger miles per month, and 5,000,000 VMT reduction per month.
Regional Trip Reduction Program (Houston)
Regional TMO and Commute Solutions program support to promote alternative commute mode choices including carpool, vanpool, transit, telecommuting, and biking. Implement community-wide marketing and public relations campaigns to educate citizens on alternative commute mode choices.
Incident Management (Houston)
TxDOT along with other transportation and safety organizations within the Houston area co-sponsor Houston’s Motorist Assistance Program (MAP), an incident management program.
ITS (Houston)
Intelligent Transportation Systems: advanced traffic management, advanced public transit system, and emergency management.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled