Annual Hours of Delay/Mile: 628,737 Annual Congestion Cost: $27,670,604 County: Harris Previous Rankings: 16
Projects
Corridor Specific:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 from Voss Rd to IH 610 W (Inner Katy- Segment 4)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsOn IH 10 from Voss Rd to IH 610 W (Inner Katy- Segment 4), reconstruct 10 mainlanes and two 3-lane frontage roads and construct 4 new non-tolled managed lanes.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-343
- Cost Estimate: $28,000,000
- Let Date: FY 2028
- Completion Date: 2031
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 from IH 610 W to Washington Ave (Inner Katy- Segment 3)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsOn IH 10 from IH 610 W to Washington Ave (Inner Katy- Segment 3), reconstruct 10 mainlanes and two 3-lane frontage roads and construct 4 new non-tolled managed lanes.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-342
- Cost Estimate: $308,000,000
- Let Date: FY 2028
- Completion Date: 2032
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 from Washington Ave to E of Patterson St (Inner Katy- Segment 2)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsOn IH 10 from Washington Ave to E of Patterson St (Inner Katy- Segment 2), reconstruct 10 mainlanes and two 3-lane frontage roads and construct 4 new non-tolled managed lanes and construct detention pond and pump station.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-344
- Cost Estimate: $520,800,000
- Let Date: FY 2028
- Completion Date: 2032
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Houston Highway Improvement Project Segment 3C-1 and 3C-2
Project Types: Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation Improvements, Other System ModificationNHHIP Segment 3C-1 and 3C-2: IH-10 at IH-69 Interchange: Reconstruct interchange to add IH-10 non-toll managed lanes and realign IH-45. IH-10: IH-69 to IH-45 North Freeway: Reconstruct to add IH-10 non-toll managed lanes for traffic bypassing Downtown. Access to local streets from IH-10 would be maintained via reconstructed general purpose lanes. Reconstruct the IH-10 interchange with IH-45. IH-10 at IH-45 Interchange: Reconstruction interchange to add IH-10 non-toll managed lanes and realign IH-45.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-599, 0500-08-001
- Cost Estimate: $2,724,000,000
- Let Date: FY 2027
- Completion Date: 2033
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 from E of Patterson St to E of Studemont St (Inner Katy- Segment 1)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsOn IH 10 from E of Patterson St to E of Studemont St (Inner Katy- Segment 1), reconstruct 10 mainlanes and two 3-lane frontage roads and construct 4 new non-tolled managed lanes.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-346
- Cost Estimate: $308,000,000
- Let Date: FY 2028
- Completion Date: 2032
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
Elysian St/IH 10 Bridge Replacement
Project Type: Operation ImprovementsIH 10, Elysian St from Commerce to Brooks, Bridge replacement.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0508-01-351
- Cost Estimate: $35,600,000
- Let Date: FY 2016
- Completion Date: 2023
- Project Data last modified: October 30, 2023
Parallel Corridors:
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
North Houston Highway Improvement Project Segment 3D
Project Types: Capacity Expansion, Grade Separation, Intelligent Transportation Systems, Interchange/Intersection Improvements, Operation Improvements, Other System ModificationNHHIP Segment 3D: IH-69: IH-45 Gulf Freeway to Buffalo Bayou: Depress and widen IH-69 from IH-45 Gulf Freeway to south of Buffalo Bayou. Reconstruct IH-69 interchanges with IH-45 Gulf Freeway. IH-45 Pierce Elevated: Re-align IH-45 from its current location on the west side of Downtown to be parallel with IH-69. Construct connectors on the west side of downtown providing access between the highway and local streets.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0500-03-598, 0500-03-601
- Cost Estimate: $1,578,000,000
- Let Date: Unknown
- Completion Date: Unknown
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 from Studemont to Houston Ave (White Oak Bayou Project)
Project Types: Capacity Expansion, Managed Lanes/Toll, Operation ImprovementsThis roadway improvement will reconstruct IH-10 from Studemont Street to Houston Avenue to raise the profile of IH-10 out of the White Oak Bayou floodway.
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-326
- Cost Estimate: $313,000,000
- Let Date: FY 2024
- Completion Date: 2028
- Project Data last modified: October 30, 2023
Project Status
Feasibility Study:
Preliminary Design:
NEPA Review:
Final Design:
Funding:
ROW Acquisition:
Construction:
Color Key
IH 10 Inner Katy Bus Rapid Transit
Project Type: Bus Rapid TransitConstruct multi-modal Bus Rapid Transit (BRT) busway including grade separation and connection to HOV lanes and transit center (METRO)
Project Details
- CSJ Number(s) or MTP Reference Numbers: 0271-07-336
- Cost Estimate: $337,106,000
- Let Date: FY 2028
- Completion Date: 2032
- Project Data last modified: October 30, 2023
Regionally:
Traffic Management Center (Houston)
Houston TranStar, a consortium of local governments in partnership with the state, is responsible for transportation operations and emergency management in the greater Houston area.
Pedestrian Improvements (Houston)
Strategically enhance bicycle and pedestrian infrastructure throughout the H-GAC region.
METRO Vanpool (Houston)
METRO supports the regional vanpool program which includes approximately 700 vans, 7,100 participants, 200,000 trips per month, 6,000,000 passenger miles per month, and 5,000,000 VMT reduction per month.
Regional Trip Reduction Program (Houston)
Regional TMO and Commute Solutions program support to promote alternative commute mode choices including carpool, vanpool, transit, telecommuting, and biking. Implement community-wide marketing and public relations campaigns to educate citizens on alternative commute mode choices.
Incident Management (Houston)
TxDOT along with other transportation and safety organizations within the Houston area co-sponsor Houston’s Motorist Assistance Program (MAP), an incident management program.
ITS (Houston)
Intelligent Transportation Systems: advanced traffic management, advanced public transit system, and emergency management.
Planned for Transit:
No improvements are currently planned.
Project Stage Status Key
— Not Begun — Complete — In Progress — Stalled